» Construction » Construction worker » ARGE Bavaria Loop » PPS Pipeline Systems » Front End Welding » Welding » Pipeline » http:www.pipelinesystems.com

ARGE Bavaria Loop Nord 40" Pipeline <br />Section between Schwandorf and Forchheim, Germany <br />for our client: <br />Open Grid Europe GmbH <br /> <br />Scope of work: <br />- 63.6 km / 39,5 mi Pipeline Construction DN 1000 / 40", DP 100 / ANSI 600# <br />- construction of 3 pig trap stations <br />- construction of 4 valve stations <br /> <br />Special features: <br />- several crossings using thrust boring technique <br />- two water crossings (culvert construction) <br />- crossing of Vils River (Microtunneling, 56") <br />- crossing of road St2394/railway 5850 (Microtunneling, 56") <br />- crossing of Main-Donau-Canal (Microtunneling, 56") <br />- crossing of motorway A 3 (Microtunneling, 56") <br /> <br />Time-frame of construction: August 2016 - October 2017 <br />http://www.pipelinesystems.com